Huber + Suhner – Pisary

Construction of a production hall with office space, external infrastructure including fire-fighting tanks, retention tanks and a sewage treatment plant.

Specyfikacja

  • Usable area: 3002 m²
  • Height of the hall: 7.5 m
  • Volume of the hall: 19,300 m³
  • Fire load, not exceeding 500MJ/m²
  • Two-story office building with an area of 600m²
  • Parking lots and maneuvering areas
  • Development of the area around the facility
  • Construction:
    • foundation directly on a foundation slab, reinforced concrete in waterproof concrete technology
    • load-bearing structure of the object “mixed” (prefabricated concrete columns, steel roof structure)

There are photo reports on our social media, updated on a regular basis.